Question
Curtis Cochran –
Can the generator controls be set to anything other than at 14 day intervals for the excercise? Could it be set for excercise every 30 days?
Upvote if this was helpful (0) Downvote if this was not helpful (0) Watch Unwatch Flag for removal
Dale Riebel –
Curtis, No. The ASCO 165 transfer switch is non-programmable, exercising every 14 days. You can disable the transfer switch exercise and do it manually every 30 days if you wish. See the ASCO 165 operators manual for instructions.
Upvote if this was helpful (0) Downvote if this was not helpful (0) Flag for removal
Question
Harry Koeppel –
generator does not shutdown after power is restored or test cycle completed.
Upvote if this was helpful (0) Downvote if this was not helpful (0) Watch Unwatch Flag for removal
Dale Riebel –
Harry, make sure the inside toggle switch is in the down position. If it is left in the middle position, it never shuts off. The outside toggle switch should be up. If that is not the issue, please contact our Service Department @ 507-357-6831 or [email protected].